This project aimed to improve Wakiso Town’s water supply by upgrading its infrastructure. Key tasks included:

  1. Installation of a 5 km main transmission line
  2. Borehole site preparation
  3. Construction of a pump control house
  4. Supply and installation of a water pump
  5. Mechanical and electrical installations
  6. Various external works

Project Information

  • Client:
    Ministry of Water and Environment
  • Project Status:
    Completed
  • Start:
    June 2012
  • End:
    December 2012
  • Category:
    Construction
  • UGX 368,318,266